S/No Client Project Description Delivery Year Status Project Site
1 NDPR Call-off Contract on Repair, Maintenance & Overhaul of Ariel Compressors 2020 Ongoing Ogbele field
2 NDPR Overhaul of the failed Ariel Compressor at Ogbele Gas Processing Plant, Rivers State. 2019 Completed Ogbele Field
3 BW Offshore Overhaul of M62 Compressor 2018 Completed Sendje Barge FPSO
4 BW Offshore 12,000 hours inspection on Compressor at Sendje Barge 2018 Completed Sendje Barge FPSO
5 BW Offshore 8k Inspection of Ariel Compressor MGC-B Compressors 2017 Completed Abo FPSO
6 Amni Vibration inspection and condition monitoring on Ariel compressors 2017 Completed Princess Aweni FPSO
7 BW Offshore Overhaul of 4no. Ariel Compressors 2016 Completed Abo FPSO
8 Seplat Supply and Installation of Superior Gas Compressor 2014 Completed Oben Gas Plant
9 Seplat O & M of Superior Gas Compressor 2014 Completed Oben Gas Plant